Sections

Water torture: Three-year pipe-replacement project in Slope will sap parking, close streets

Water pain: The city is replacing pipes beneath St. Johns Place, Flatbush and Sixth avenues, and Baltic Street over the course of three years, resulting in the temporary loss of parking, closed streets, and loud noise.
Brooklyn Paper
Share on TwitterTweet
Share on Facebook
Subscribe

Don’t miss our updates:

Talk about wet work!

Park Slopers can expect three years of racket, road closures, and parking woes as workers dig up neighborhood streets to renovate aging city pipes below them.

The Department of Design and Construction’s water main–replacement project, called BED798, kicked off on Jan. 31, and will continue through the summer of 2021 as plumbing beneath roadways including St. Johns Place as well as parts of Baltic Street and Flatbush and Sixth avenues is revamped.

Workers will cut trenches through the asphalt between 7 am and 6 pm on Mondays through Fridays in order to lay new pipes ranging from eight to 72 inches in diameter, and local car owners should keep an eye out for fliers announcing temporary road closures and parking restrictions, according to agency spokesman Ian Michaels, who said all affected streets will remain accessible to pedestrians throughout the job.

Residential and commercial buildings on blocks where work is taking place will lose water service during certain periods, but the design-and-construction department will alert locals in advance, and any interruptions will be restored by the end of the work day during which they occur, Michaels said.

The pipe-replacement project also includes the installation of combined sewers, catch basins, and manholes, in addition to reconstructing a triangular pedestrian plaza bounded by Eighth Avenue, Flatbush Avenue, and St. Johns Place.

Similar work is underway on plumbing beneath Leonard Street in Williamsburg, and last week the design-and-construction department announced it would use an installation process called “slip lining” — in which new, smaller pipes are threaded through larger, older ones — to shave one year off the job, which will now finish in 2019 instead of 2020.

But that technique won’t work in Park Slope, Michaels said, because the pipes being replaced there are too bendy, making it difficult to insert new tubes inside them.

Any residents who want to contact the city about the water-main-replacement project in Park Slope can contact its community liason Niel Patel at (347) 889–5271 or bed798ccl@gmail.com.

Reach reporter Colin Mixson at cmixson@cnglocal.com or by calling (718) 260-4505.
Updated 5:49 pm, July 9, 2018
Today’s news:
Share on TwitterTweet
Share on Facebook
Subscribe

Don’t miss our updates:

Reasonable discourse

Joe from Gowanus says:
This article fails to mention what caused the need for this expensive upgrade. This project is being completed in advance of the rezoning of blocks north of Union between 2nd-4th Avenues. The 10,000 new apartments need larger pipes to accommodate all of that additional sewage!
Feb. 14, 8:50 am
SwampYankee from ruined Brooklyn says:
so let me get this strait. Complete L train tunnel rehab.....15 months. Sewer pipes on a few streets in Brooklyn over twice as long? Yeah, sounds about right
Feb. 14, 9:22 am
Tyler from pps says:
Swampy -- Why do you think tearing up, replacing and maintaining service the whole time for a few miles of pipe is less complex than a subway tunnel rehab? (A tunnel that is completely closed during the work)

You're not the sharpest knife in the drawer, Swampy, but you don't have to keep providing evidence.
Feb. 14, 12:08 pm
freddy from slope says:
joe:

i am excited to find there is a second avenue north of union street.
did they fill the gowanus?
Feb. 15, 12:38 am
Tyler from pps says:
Not just that they've apparently filled in the Gowanus, freddy....

Can you imagine the shock and horror of higher density housing in the Downtown area of 2.6 million people!? What are they thinking increasing the density of the downtown core?!
Feb. 15, 11:16 am

Enter your comment below

By submitting this comment, you agree to the following terms:

You agree that you, and not BrooklynPaper.com or its affiliates, are fully responsible for the content that you post. You agree not to post any abusive, obscene, vulgar, slanderous, hateful, threatening or sexually-oriented material or any material that may violate applicable law; doing so may lead to the removal of your post and to your being permanently banned from posting to the site. You grant to BrooklynPaper.com the royalty-free, irrevocable, perpetual and fully sublicensable license to use, reproduce, modify, adapt, publish, translate, create derivative works from, distribute, perform and display such content in whole or in part world-wide and to incorporate it in other works in any form, media or technology now known or later developed.

First name
Last name
Your neighborhood
Email address
Daytime phone

Your letter must be signed and include all of the information requested above. (Only your name and neighborhood are published with the letter.) Letters should be as brief as possible; while they may discuss any topic of interest to our readers, priority will be given to letters that relate to stories covered by The Brooklyn Paper.

Letters will be edited at the sole discretion of the editor, may be published in whole or part in any media, and upon publication become the property of The Brooklyn Paper. The earlier in the week you send your letter, the better.

Keep it local!

Stay in touch with your community. Subscribe to our free newsletter:

Optional: