Environmentalists say that the new ferry line slated for Coney Island Creek could risk the health of swimmers and fishers who frequent the area.
Photo by Charles Denson

An environmentalist accused a city agency of underplaying the expected impact of a ferry line planned for Coney Island in official government paperwork.

The quasi-governmental Economic Development Corporation, which runs the city’s ferry system, said in the state’s requisite permit application that the ferry dock would fit seamlessly into Kaiser Park, the secluded greenspace where the city is planning to construct the terminal.

The reps also wrote that the dock won’t dramatically “increase traffic” to the area, and that the terminal’s proposed location is not near a former waste management site.

Coney Island environmentalist and historian Charles Denson disputed those claims.

“Will the proposed action result in an increase in traffic above current levels? You answered no!” said Denson at a meeting about the ferry. “That is false.”

There is a former “waste management” site in the area, Denson added. Calvert Vaux Park, located on the other side of the creek, was used as an illegal dumping ground for decades, and a Sanitation Department incinerator once operated across from that park, he said. 

EDC rep Jennifer Cass said that the park was not formally considered a waste management site, but did not further address Denson’s accusations. 

The back-and-forth came during a Dec. 14 meeting about the new Coney Island ferry line, which is slated to be up and running by the end of 2021. The ferry make stops at Kaiser Park, Bay Ridge, and lower Manhattan — cutting the arduous trip from Coney Island to Manhattan to a mere 35 minutes. 

Many residents say they’re in favor of the ferry, but environmentalists charge that the terminal’s construction will stir up dormant pollutants in Coney Island Creek, which is currently under consideration for Superfund status

coney island ferry
The new terminal will be built on the existing Kaiser Park pier.EDC

Dredging during construction could potentially put the health of residents who swim, fish, or hold religious ceremonies along the waterway at risk, environmentalists say.

To try to assuage these fears, representatives from EDC spoke about their plans to mitigate contamination during the Dec. 14 meeting.

“What we’re doing is being done safely,” said James Wong, the executive director of EDC’s ferry division. “Just making sure we’re keeping to promises and making sure theres minimal destruction to aquatic life.”

Dredging will begin in January to ensure the creek is deep enough to accommodate the ferries, Wong and other representatives said. Workers will dredge up to two feet of silt at only one section of waterway by the mouth of the creek, where representatives claim there are no detectable toxins, according to EDC’s presentation.

To refrain from disturbing aquatic life, dredging will stop during the flounder and horseshoe crab spawning seasons, and workers will use a “turbidity curtain” and “environmental bucket” to ensure that the upended soil doesn’t spread to rest of the creek.

But environmentalists claim that these so-called safeguards are far from foolproof.

coney island ferry
EDC representatives said that workers will dredge two feet of silt from the mouth of Coney Island Creek in order to build the ferry.EDC

“Curtains flare at the bottom; they don’t contain the toxins. Environmental buckets leak,” charged Ida Sanoff at the meeting, citing a 2015 video of contractors lifting up an environmental bucket full of contaminated sediment, which is seen leaking back into Gravesend Bay. 

Denson blasted EDC’s choice to build the terminal in the creek, and spoke about the alleged “falsehoods” in EDC’s permit application, citing a letter he had written the state’s Department of Environmental Conservation.

“NYCEDC’s permit application is filled with falsehoods designed to obfuscate the true impact that this project will have on the State’s Tidal Wetlands habitat and the water quality of Kaiser Park and adjacent Coney Island Creek Park,” Denson wrote in his letter. 

Though EDC has long claimed that the ferries are too small to dock safely on the open ocean, community members demanded that the agency find a way to build the terminal on Coney Island’s beach, which is a much more common tourist attraction than the creek. 

“It may cost some more money, that’s true,” said Jeff Sanoff, who co-chairs the community board’s environmental and sanitation committee. “But I can’t believe the engineers at EDC can’t think of a solution when we put a man on the moon.”

Locals also argued that the agency is pushing a quick timeline for construction and minimizing community input in order to finish the project by the end of Mayor Bill de Blasio’s tenure.

Stop trying to sell us a cheap and dirty plan,” said community activist Craig Hammerman. 

Correction [Dec. 17]: A previous version of the article said that Jeff Sanoff is the chair of Community Board 13’s transportation committee. He is actually the co-chair of the environment and sanitation committee. We regret the error.